Sometimes a planner is not only interested in the timing and duration of an operation but he also wants to see the number of work packages needed by a resource to complete an operation. Our Gantt component VARCHART XGantt allows visualizing the individual working times of a resource in the operation bar in an optical appealing way. Read the following blog post to learn how this works.
An operation bar stretching over a certain persiod (e.g. several days) is usually based on two different time spans:
a) Duration of the operation, i.e. the time span from its beginning to its end, no matter which working calendar is currently valid.
b) Work effort, that means the real working time spent on the operation. This figure usually is smaller than the duration, since not every operation will be worked on continuously (7 days/week, 24 h/day).
So the developer of Gantt charts faces a visual dilemma: Is he to focus on a) the total duration of an operation or b) the visualization of the concrete work effort.
Displaying an operation with the single work packages, i.e. the individual working times, can be realized by a combination of different layers to be selected in VARCHART XGantt. The underlying thought in this is to visually stack bars. For this, a continuous bright layer (total duration) has to be defined and an interrupted dark layer (working times) be placed over it. As a consequence, the brighter background color will shine through during work-free periods
The bar now shows both the individual working time of the resource and the total duration of the operation it is currently working off.
4 or 5 single layers are needed, depending on whether logical links are to be shown as well.
Basically, the following applies:
[Layer_1] | Name=Top | NonWorkIntervalShape=VC_NIL
[Layer_2] | Name=Below (background) | NonWorkIntervalShape=VC_NIL
[Layer_3] | Name=Below (working time) | NonWorkIntervalShape=VC_INVISIBLE
[Layer_4] | Name=Below (frame) | NonWorkIntervalShape=VC_NIL
[Layer_5] | Name=Imaginary middle | NonWorkIntervalShape=VC_NIL
The “Specify Bar Appearance” dialog of the Gantt component VARCHART XGantt lets you define different layers. On the property page “Objects” click “Layers” to open the below dialog:
Five layers need to be defined for visualizing the operation bars with individual working times:
1) “Top”
Did this blog post help you solving a problem you face in every day scheduling? Do want to get more Gantt Best Practice tips on how to make your Gantt chart more effecitve? Then read our blog post How to integrate a shift calendar in the time scale.
Not yet using VARCHART XGantt? Get started with your trial today: